Skip To Main Content

Module 2: Forming the Project Team (OPM and Designer)

Module 2 involves forming the project team by selecting an Owner's Project Manager (OPM) and a Designer.

 

MSBA Module 2 Guidelines

 

OPM Process

A subcommittee of 6 members of the School Building Committee met from July-November, 2012 to select an Owner's Project Manager (OPM). The selection of Skanska, USA, with Maryanne Williams as the lead, was approved in December, 2012.

 

RFS for OPM

MSBA OPM Approval 12/5/12

Skanska Executed Contract

Skanska Contract Attachment A 12/6/12

OPM Selection Update 1/4/13

 

Designer Selection Process

A subcommittee of 5 members of the School Building Committee met from January-March, 2013 to select a Designer. The selection of Kaestle Boos Associates (KBA) was finalized in April, 2013.

 

RFS for Designer Jan., 2013

Designer Selection Process Schedule 1/8/13

KBA Presentation 1/8/13

KBA Designer Contract 4/8/13