Updates: 2014-15

  • 2014-15
    Submitting the Preferred Schematic Report
    The District  submitted  the Preferred Schematic Report to the MSBA on June 11, 2015.  The MSBA Board will review this and make its determination on August 6, 2015. Details on the submission can be found in Module 3: Feasibility Study, Preferred Schematic Report.

    Voting on Preferred Schematic Option: School Committee
    At their May 19, 2015 meeting, the School Committee voted to approve the recommendation of the School Building Committee for a Preferred Schematic Option for a New School with a Design Enrollment for 628 students, and to authorize Skanska, USA, the Owner's Project Manager, to submit the Preferred Schematic Option and accompanying Report to the MSBA on behalf of the District, no later than June 11, 2015.  Read press release here.

    Voting on Preferred Schematic Option: School Building Committee
    At their May 11, 2015 meeting, the School Building Committee voted on the Preferred Schematic Option they would recommend to the School Committee.  Presentation materials can be found here.

    Community Presentations
    Members of the Minuteman School Committee, the School Building Committee, and the Administration have developed a schedule of community presentations to inform stakeholders of issues related to the Building Project and to gather questions and feedback that will inform the School Committee as they prepare to take their vote on the preferred option to recommend to MSBA. This vote is scheduled for the May 19, 2015 School Committee Meeting. Related documents are found below:

    Sample Presentation: Acton
    Building Project: Why We Need to Act (video)
    Enhancing Our Education Program:  Career Academy (video)
    Community Presentation Schedule 4/17/15
    Report on Community Presentations (5/6/15)
    Frequently Asked Questions